|
|
 |
Projects
Plummer Creek Wetlands Restoration
The work performed for this effort was part of a wetland restoration / improvement project
funded by the Tribe and Idaho IDEQ through an EPA 319 Program grant. The Plummer Creek
project was the restoration of wetland functions in a 3.3 acre delineated wetland located
on the south side of the City of Plummer. This involved the construction of two low
earthen check dams and an "island flow deflector", excavation to create new meander
channels and enlarge an existing pond, vegetative plantings and an observation trail.
The construction work was completed in October 2002, the planting in November and the trail
construction in December.

Figure 1. Topographic map of a portion of the Plummer Creek watershed within the Coeur d'Alene Reservation showing the
Plummer Industrial Park wetland restoration site
The site of this work is part of a Tribal property referred to as the Plummer Industrial Park.
The restored wetland area is to be a natural, green space habitat area within the proposed
light industry / commercial / office park. The Plummer Creek watershed above the project
site is shown on Figure 1.
Plummer Creek flows through this site but its channel has been straightened and the riparian
area has been degraded to the point that it provided limited flood flow attenuation, habitat
or water quality improvement (see Photograph 1). These values were to be
restored primarily through the construction of two low check dams that would make use of the
existing topography to provide for enhanced flood storage and sediment trapping as well as
seasonal open water habitat. The check dams would allow for fish passage in order to meet
the Tribe's goals for the restoration of native salmonid use of this stream. The "island
flow deflector" was designed to block the existing stream channel and direct water entering
the wetland site into the enlarged pond with flood flows being directed into a new meander
channel that would lead to the upper check dam.

Photograph 2. Plummer Creek Wetland site, pond construction, October 15, 2002.
|
The Plummer Creek watershed above the wetland site is a relatively undisturbed area covering
approximately 2,500 acres. The length of the watershed is just less than three miles, 15,300
feet, along the north-south axis. The lower elevation (at the project site) is approximately
2,715 feet, while the upper elevation at the south limit of the basin is 3,371 feet. The
upper elevation at Plummer Butte is 4,145 feet. Thus the average slope within the watershed
is between 4% and 9%.
General vegetation types in the watershed include approximately 600 acres of pasture or
cultivated for hay production and approximately 1,900 acres of woods/forest or shrubs. There
are fewer than ten homes or farmsteads in the watershed and few paved roads (US 95 being the
primary exception). Considering the soils, slope and vegetation in this basin, the expected
runoff from the design storm (25 year, 24 hour peak storm) is 0.43 inches in depth which
results in a total runoff volume of 89.6 acre feet and a peak discharge of 159 cubic feet per
second.

Figure 2. Plummer Creek / Wetland site layout (not to scale)
|
Following research into possible wetland restoration techniques, the "check dam" design was
developed. This is an earthen embankment dam topped with a rocked two-stage broad crested
weir. This is a self-regulating structure designed to temporarily retain flood flows thereby
raising the soil water content. Based on the topography of the site, two check dams were
desired. Due to the lack of soil available on or near the wetland site that could be used
to build the check dams, soil was to be imported; further, that soil had to contain a clay
content (approximately 20% by weight) that was appropriate for compaction in the embankment.
Fortunately, the planned transport of rock from a commercial pit near Plummer to a streambank
restoration site in the Hangman Creek watershed provided an opportunity to utilize trucks to
bring such clay soils back on their return trip.
While there was an existing topographic survey map that had been prepared showing the entire
Industrial Park site, this did not show sufficient detail of the wetland features to be used
for the final design of the check dams. As a result, a level survey was conducted which focused
on the elevations of the stream channel bottom and the ground surfaces where the two check dams
were to be placed. This elevation information was tied into the existing survey datum and
allowed cross section and longitudinal profiles to be plotted on which the check dams could be
shown.

Photograph 3. Plummer Creek Wetland site, island flow deflector, October 24, 2002.
|
The next important task to be performed on this project was a vegetation survey of the project
site and an upstream reference site. These were necessary to establish the existing condition
in the area to be restored and also provide targets for species distribution in the completed
project. The vegetation survey was performed as a walkthrough of the entire site with
identification of all visible plant species. At the same time plants were surveyed, an
estimation of their coverage was made as a means of establishing the dominant species. Because
there were differences apparent in the predominant vegetation types found on different parts of
the wetland site, the survey was divided into five areas and the coverages recorded referred to
the given “Veg. Area” only, not the entire site. Finally, a wetland indicator status was
determined for each identified plant species. These indicators provide some insight into the
extent that each area is currently supporting key wetland species.
In order to describe the Plummer wetland restoration process for potential reviewers or interested
parties, the Plummer Industrial Park Wetland Restoration Plan was prepared. The basic content of
this Plan followed the 1993 Washington Department of Ecology publication entitled: Restoring
Wetlands in Washington; A Guidebook for Wetland Restoration, Planning and Implementation. This
included a detailed site assessment for both the project site and the upstream reference site.
Features of the site assessment included topography, soils, ecological communities (vegetation,
exotic species, wildlife and fish), hydrology, boundary delineation, water quality and existing
wetland values and functions. Following the site assessment, design criteria were explained.
Design criteria included performance standards and specific design features of the various
desired structures. The Restoration Plan also addressed general procedures for maintenance of
constructed features and basic monitoring efforts to allow documentation of changes in the
wetland system over time and success of the restoration techniques.

Photograph 4 Plummer Creek Wetland site, constructing check dam across existing creek channel October 21, 2002.
|
Following completion of the Restoration Plan, a Joint Application for Permits was prepared and
submitted to the US Army Corps of Engineers. Also, in support of hiring a contractor to
construct the desired restoration features, Plans and Specifications and bid solicitation
documents were prepared. Included with these documents, a site map (see Figure 2) showed the
location of the proposed restoration features.
Work performed on this project in 2002 included the preparation of a bid solicitation for
the construction work; touring potential contractors through the project site; improvement of
the access into the site using Tribal and Plummer Forest Products (operators of the adjacent
log yard) staff and equipment; selection of a contractor (Professional Operators Company of
Lewiston, ID) and pre-construction surveying and staking. Actual Construction work began
October 15 and was completed in approximately two weeks. Heavy equipment used included a
315B CAT Excavator (with 40" toothless bucket and thumb), 550 G John Deer Dozer and 10 cubic
yard dump truck.
The construction work progressed generally from the upstream end of the project downstream,
starting with the deepening of the existing pond (see Photograph 2). The predominantly clay
soil removed from this location was trucked and spread on the upland area to the west of the
wetland boundary. The new depth of the pond is 10 feet below the surrounding ground surface
and this depth meets a layer of gravelly clay. There was a small amount of water entering the
excavation from approximately the six-foot depth. The surface dimensions of the finished pond
are approximately 80 feet north to south and 60 feet east to west.

Photograph 5. Plummer Creek Wetland site, constructing spillway in upper check dam, October 24, 2002.
|
Next, two new channels were dug to connect the existing channel with the pond; one for inflow
one for outflow. Then the "island" could be constructed, this being simply an earthen plug in
the channel. It was necessary to pump the water out of the channel above the island to allow
the placement of geotextile and the rock face of the island which constituted the "flow
deflector" (see Photograph 3).
The construction of the upper check dam involved digging a two foot by four foot core trench
the length of the dam, including across the existing stream channel, and then filling /
compacting this trench with imported soil. This was done progressively working east to west.
The core trench across the stream channel involved placing a temporary plug in the channel both
above and below the core trench location and pumping the water out between these (see
Photograph 4). Since the imported soil was too dry for acceptable compaction, this creek water
was pumped (sprayed) into the trench as the soil was being pushed in with the dozer, so it did
not need to be disposed elsewhere. Compaction of core trench and embankment dam was accomplished
using the dozer.

Photograph 5. Plummer Creek Wetland site, constructing spillway in upper check dam, October 24, 2002.
|
The construction of the embankment followed the completion of the core trench and this was
completed on October 22nd. Then the compacted material was removed at the spillway location.
The toothless bucket was invaluable for this because it allowed a precise cut in the shape and
dimensions of the spillway. On this cut a non-woven geotextile was placed and then a layer of
rock, following the gradation provided in the project specifications (see
Photograph 5).
The lower check dam was constructed by shaping the existing fill that formed a vehicle access
from the adjacent log yard. This fill was a mixture of soil and small rock and was extremely
tightly compacted. However, the existing 36-inch culvert through this fill had to be removed
and this excavation was re-filled and compacted with a mixture of the soil / rock material and
imported clay soil. Compaction in this area was achieved using the excavator bucket. The
spillway through the lower dam was again cut out of the fill and covered with geotextile and
rock.

Photograph 7. Plummer Creek Wetland site, footbridge construction and plantings near upper check dam, December 20, 2002.
|
The final construction performed using heavy equipment was the digging of new meander channel
between the flow deflector and the upper check dam (this being a flood or overflow channel)
and between the upper and lower dams (see Photograph 6). In addition, a shallow pool (less than
two feet deep) was dug above each of the dams. The size of these (at low flow) is approximately
20 feet by 30 feet, above the upper dam, and 30 feet by 60 feet above the lower dam. These
shallow pools connect with the existing stream channel to provide a considerable increase in
open-water area on the site.
Revegetation work (applying and mulching a native grass & rush mixture and planting trees
and shrubs) followed the heavy construction during November. Finally, a foot bridge was
constructed by Tribal Fisheries staff over the upper check dam in December
(see Photograph 7).
|
|
|